Brant Park

Located on the northeast corner of Adelaide Street West and Brant Street in downtown Toronto across from St. Andrews Park, Brant Park consists of 243 units over 11-storeys. The condominium apartment project is a collaboration between Lamb Development Corporation and Fortress Real Developments.

Registration of the building took place in the first quarter of 2017 and Fortress completed its role in May of 2017. See a visual timeline of The Brant Park on our progress update page.

The Brant Park

Fortress is proud to be a project partner on The Brant Park by Lamb Developments. Located on Adelaide Street West in the King West neighbourhood of downtown Toronto. This building brings bold style to the area and overlooks St. Andrew's park to the west.

Completed Building Exterior

Completed Building Interior

Rendering To Reality

We are very proud of Brant Park," proclaims Fortress CEO Jawad Rathore, "Our partnership with Lamb has been tremendous so far with five completed projects, three currently under construction and two scheduled to break ground this year. We have a busy 2017 ahead of us with several projects completing and many ready to start construction.

Project Updates

January, 2017

Brant Park is nearing full occupancy, as there are now only a couple unsold units, which are available for approximately $820 per-square-foot. Interested buyers are encouraged to contact Brad J. Lamb Realty for more information. Registration is expected in the first quarter of 2017. Visit www.thebrantpark.com for more information.

October, 2016

Occupancy has commenced at Brant Park and the project is now over 95% sold, with developer inventory selling for over $700 per-square-foot. Lamb Development Corporation expects the building to register before the end of 2016. The model suites are available to view on weekends only at 434 Adelaide Street West.

July, 2016

Lamb Development’s Brant Park at 434 Adelaide Street West is now occupied and 86% sold. Model homes are now available to view.

April, 2016

Brant Park is approximately 85% sold and occupancies have started. A fully furnished model suite is now complete, and remaining units start from $282,900.

January, 2016

Brant Park is now over 80% sold. The hording around the project has come down, all stucco has been applied, all windows are in and the concrete sidewalks are installed. Pre-delivery inspections for purchasers have commenced, with occupancy scheduled to start in the first quarter of 2016.

October, 2015

Bluescape Construction is installing the exterior cladding on Brant Park, which has been topped-off. Interior finishes are now being completed for a projected occupancy in the spring of 2016. All of the ground-floor retail space has been sold to an investment group, and Ashlar Urban Realty is currently pre-leasing the space on their behalf.

July, 2015

Brant Park has been topped-off, with windows and exterior finishes now being installed on the building. Interior finishes will then be completed this fall.

April, 2015

Construction continues at a brisk pace at The Brant Park, where concrete works and framing is currently taking place on the 9th floor of this 11-storey condominium building. Once topped off, windows and interior finishing will begin. Brad J Lamb Realty continues to sell units in this project without actively marketing the development, which demonstrates the strength of the location, design and builder reputation at the project.

January, 2015

Construction of the underground parking was completed in October. Bluescape Construction Management Inc. is working closely with the Lamb Development Corporation team on the project, which has now reached the second level.

October, 2014

Construction is moving quickly at Brant Park, as the underground levels are now complete and work has reached grade. This project is approaching 80% sold.

July, 2014

Shoring and excavation work is now complete at The Brant Park. A crane is now erected and work on the underground parking levels is underway. The project which is over 70% sold, will be releasing its final block of suites later this year.

May, 2014

The construction crane has now been erected.

March, 2014

Almost 75% of the way down, excavation is nearing completion at the Brant Park. The three underground levels will house 120 parking spaces for the residents and visitors.

December, 2013

With demolition complete, the project secured construction financing in late October. Site servicing has commenced and excavation is scheduled to start before the end of the year.

September, 2013

Demolition on site began in late July. The Blue Bird building off Adelaide Street West is no more, as the site and sales centre have been demolished, and the site has been cleared in anticipation of a fall construction start.

May, 2013

The project has achieved over 150 unit sales. Some minor site work has begun on site and as soon as the construction financing is finalized, demolition will begin. Plans are to have work starting on site this summer.

February, 2013

The project is currently 55% sold, with construction expected to start shortly.

November, 2012

The sales centre continues to be open six days a week. Financing has been committed for construction and a start date for demolition has been targeted for 2013.

August, 2012

A new set of drawings provided by their architects has been submitted to comply with the Ontario Municipal Board variances, which required them to submit the original proposed amenity area and provide grade bicycle parking. They are expecting to receive a revised report from the City in approximately 24 days.

April, 2012

The project was officially launched earlier in the month and sales are moving along very well.

May, 2011

Land closes May 30th, 2011.