6th & Tenth is a 31-storey point tower in Calgary’s Beltline district, just south of the city centre at 663 10th Avenue Southwest. The condominium apartment project by Lamb Development Corporation consists of about 230 one bedroom to two bedroom plus den suites ranging in size from approximately 450 sf to 1,950 sf.

The sales at 6th & Tenth were launched in the fall of 2012, with pricing starting from the low $200s to over $1 million. Construction started in 2014, and first occupancies occurred in the spring of 2017.

Common building amenities include an outdoor patio and a landscaped ‘forecourt’ park with water features. Retail, including a 5-star restaurant is planned at grade. This is the first project in Alberta for Lamb Development Corporation, in collaboration with Core Architects, and The Design Agency. Sales are by Brad J Lamb Realty.

Building A High-rise in Calgary

Brad Lamb talks about venturing to Calgary and bringing his high-style design to a new city.

It appears to me that it has the potential to be this little Manhattan.

Calgary Hearld

Project Updates

August, 2018

All sold units are occupied and the developer has an inventory loan in place for the balance of the units. A local salesperson has been hired to assist in selling the balance of the units.

April, 2018

Occupancy is complete at this high-rise development in downtown Calgary and registration took place in March. This project is over 80% sold. For interested purchasers, units are still available for purchase ranging from 449 sf to 1,650 sf, priced from $265,900 to $1.3M.

January, 2018

Occupancy is now complete in this high-rise development in downtown Calgary, with registration anticipated in the first quarter of 2018. There are several great units ranging from 449 sf to 1,650 sf, priced from $265,900 to $1.3 million available for purchase and a model suite is now available for viewing.

October, 2017

Occupancy continued in the second quarter, and Scott Construction continues to put the final touches on the project. A model suite is now available for viewing. Remaining units range from 449 sf to 1,650 sf, priced from $265,900 to $1.3 million. Interested purchasers can call 403-710-6665 to book an appointment.

July, 2017

Purchasers began taking occupancy at 6th and Tenth in June as Scott Construction continues to put the finishing touches on the podium and upper-floor suites. A fully decorated and furnished model suite will open in July. The building is approximately 85% sold. Email info@6thandtenth.com to make an appointment to view the show suite.

April, 2017

6th and Tenth is nearing completion, with the building entirely closed in and suite interiors being installed. Residents will occupy their units in May/June. Remaining suites range from approximately $300,000 to $600,000 and start at 449 sf. Prospective purchasers can go to www.6thandtenth.com or call 403-239-5511, for unit availabilities.

January, 2017

6th and Tenth is now topped off with windows installed up to the 27th floor, the building envelope will be complete in early 2017. Kitchens and bathrooms are now being installed, and occupancy is scheduled for the spring of 2017.

October, 2016

Construction on 6th and Tenth has reached the 26th floor, with windows installed up to the 18th floor. First occupancies are anticipated for early 2017. Direct sales enquiries to 403-239-5511.

July, 2016

Scott Construction has completed the 14th floor at 6th and Tenth in Calgary. The cladding and window walls are now being installed. Suites start from $215,900, with penthouses from $1,086,900. First occupancies are scheduled for early 2017. Visit www.6thandTenth.com for more information.

April, 2016

Construction on 6th and Tenth has reached the 5th above grade level. The first occupancies are scheduled for 2017. Select floorplans are still available, interested purchasers are encouraged to email info@6thandtenth.com.

January, 2016

Construction on 6th and Tenth has reached grade level, and occupancy is scheduled for 2017.

October, 2015

The Scott Construction team has poured the elevator pit footing at 6th & Tenth, and the crane base is now in place. The excavation at this development is the third deepest hole in the history of Calgary construction.

July, 2015

Excavation at 6th and Tenth is now complete. A crane has been erected, and the building will begin to reach grade by the end of this year.

April, 2015

Shoring and excavation work for the underground levels is nearing completion with footings and concrete pouring to begin later this spring.

January, 2015

Excavation started in November and is now two levels below grade.

October, 2014

Construction is underway at 6th and Tenth in Calgary. Site clearing was completed in August by Scott Construction, and heavy machinery is now on site.

July, 2014

Construction is expected to commence shortly. Demolition was completed on site in July with shoring and excavation work to start in the next 30 days. The project is over 80% sold, and is expected to take approximately two years to complete.

April, 2014

Due to the hot Calgary market, sales were very strong towards the end of last year and the project has now surpassed its construction sales threshold. Hoarding will be installed on site shortly, and excavation work is expected to begin in the next 60 days.

December, 2013

The project has seen a surge in sales over the last quarter and is on track to begin construction in 2014. In November there was an official unveiling of the public art piece that will be a beautiful addition to the streetscape in downtown Calgary.

May, 2013

Calgary remains consistently a strong market for real estate in Canada and it is expected the remaining pre-sales are completed by Q4 2013. Construction is scheduled to begin next year.

February, 2013

Sales are continuing at a moderate pace in time to start construction, with 55% of the units now sold.

November, 2012

The sales centre is complete and sales are proceeding at a steady rate. To ensure ‘bona fide’ sales, LDC and FRDI are requiring a full 15%+ cash deposit schedule. Most condo projects in Alberta will take 5% down and 10% ‘bond’; this is a risky practice that has sunk or stalled many developers as there is little genuine commitment by the unit buyers. Sales are expected to continue at a moderate pace in time to start construction.

August, 2012

Lamb Development Corp. is currently working diligently to put final touches and aggressively prepping the public for the official launch of 6th and Tenth, scheduled for the first weekend of September. They are predicting quite a number of sales from it in addition to the 30% in presales already done. The sales centre has now been completed.

December, 2011

Application for zoning has been submitted.

November, 2011

Project launch.